| What
it is |
How
to |
Templates/
Examples |
|
| |
| How to: Manage
Budget
Recommended actions and strategies
The table below describes several steps you can
take to manage a project budget.
|
What to do |
How to do
it |
1 |
When tracking project finances identify budget
variances as they occur |
Focus on the following financial components of
the project:
- The baseline budget – the
budget as approved by the project sponsor. (Each
time the sponsor approves a new budget, the new
approved budget becomes the baseline budget for
tracking project costs.)
- The total cost of changes as
approved through change control.
- The cost estimate to complete remaining
tasks. Revised estimates from project
team members to complete remaining tasks.
- The actual costs to date expended
on all project tasks.
- The expected at end is the current budget projection for completing the project and is the sum of the actual costs to date plus the cost of any approved changes and re-estimates to complete remaining tasks.
- The variance is the current baseline minus the cost expected at end . A positive variance means the actual cost of the project is less that the budgeted cost. A negative variance means the actual cost of the project is greater than the budgeted cost.
Note: The level at which you budget and track actuals
depends upon the nature of your project and the requirements
of the project sponsor. |
2 |
Understand the reasons for either positive or
negative variances in the budget |
Work with the project team to determine causes
of variances.
Positive variances may indicate:
- Project behind schedule
- Ineffective budgeting
- Legitimate changes
Negative variances may indicate:
- Excessive changes
- Schedule delays
- Ineffective budgeting
|
3 |
Make adjustments to the budget to reflect any
changes or revise the cost estimates |
When adjusting the budget pay particular attention
to:
- Scope changes
- Staff changes
- Schedule changes
Caution: Be careful adjusting a budget to a lower
cost. If some tasks cost less, others will probably
take more time. |
4 |
Assess impacts to project scope and requirements |
Budget adjustments (either more or less funding)
may impact what the project can deliver. |
5 |
Communicate any budget changes or issues to the
project sponsor |
Let the sponsor know about any changes to the
budget, the potential impact of these changes and
resulting actions. |
6 |
Get approval from the project sponsor for any budget
adjustments |
Adjusting the budget results in a new baseline and
requires approval from the project sponsor. |
|
|
| |
Printer-friendly
<< Return to top
Updated February 1, 2006 - v1.0