|
What to do |
How to do
it |
1 |
Determine the tasks to be placed in the schedule |
Refer to the tasks identified in the work breakdown
structure. |
2 |
Determine the relationships among the tasks |
Identify tasks that must be completed before other
tasks can begin. Identify tasks that can be done
while other tasks are being performed.
- A network diagram (a precedence diagramming
method) can be used to diagram the dependencies.
|
3 |
Assign each task to specific staff |
This establishes ownership for the task.
Assigning the right person to the right task is
one of the most important factors in a project’s
ultimate success. |
4 |
Estimate the amount of effort required for each
task |
Work with individual team members or others who
have experience with this type of project.
Base the estimate on an assumed level of skill.
Document
assumptions used in estimating. |
5 |
Consider the other variables that go into building
the schedule |
Example variables to consider:
- Project Constraints
- Assumptions
- Lead and lag time (delay) of materials
- When, where or how the task must be performed
- Project risks
- The realities of vacations, meetings, discussions
and staff interactions and any ongoing responsibilities
team members may have.
- Staff Training time
|
6 |
Build a time reserve into the schedule for contingencies
and unforeseen events |
A contingency is a specific provision for unforeseeable
elements that could cause schedule delay.
How much time contingency to allow can depend
on:
- The degree of acceptable risk for delays
- The completeness of the project definition
- How well the work will be managed
A good rule of thumb for schedule contingency is
20%, but a project can include more or less based
on the factors above. |
7 |
Identify the project’s critical path |
The critical path is a project management technique
that analyzes what activities have the least amount
of scheduling flexibility (i.e., are the most important)
and then predicts project duration based on the activities
that fall along the “critical path.”
Activities that lie along the critical path cannot
be delayed without delaying the finish time for
the entire project.
If the critical path exceeds
a required deadline, review methods to shorten
the critical path. |
8 |
Check to see if staff is over-allocated |
If staff is over allocated, figure out a way to
level the staff so they are allocated the right amount
of work.
Possible actions:
- Modify the schedule to accommodate the constraint
- Provide additional resources for the task
- Reduce task or project scope
- Make any adjustments to the staffing plan
Caution:
There is an overhead cost for bringing new staff
up to speed. Not all staff is truly interchangeable.
The skill level of the new person may affect
the time to complete and the quality of the work.
Contract staff may need more oversight. |
9 |
Repeat steps 3 and 5-8 until a baseline is established. |
Developing the project schedule is an iterative
process. |
10 |
Place the schedule information in a Gantt chart |
Place the tasks, milestones, relationships, staff
assigned, durations and work estimates in a Gantt
chart to show the detailed timing of the project.
A Gantt chart graphically represents a project
by showing each task as a horizontal bar whose
length is the time needed to complete the task.
Various project management tools can generate Gantt
charts.
Other formats can be used to display the
schedule information based on the needs and preferences
of your customer. |